Enova has selected Fortius Offshore Wind AS and Fram Wind Solutions AS as winners of its competition for small-scale commercial floating wind. The two projects, with a planned combined capacity of approximately 74 MW, are set to be realised at METCentre outside Karmøy.

Two new floating wind projects are moving towards realisation in Norway after Deep Wind Offshore and Fram Wind Solutions were selected for support through Enova’s competition for small-scale commercial floating wind.

Both projects are planned for METCentre outside Karmøy. Each has a planned capacity of approximately 37 MW, giving a combined capacity of around 74 MW. 

The decision has been eagerly awaited. Five companies applied for a total of NOK 9 billion in support by the February deadline, with each project eligible to receive up to NOK 2 billion. A decision was initially expected in May. Now, at the end of October, the winners have finally been selected.

See Enova's own press release (in Norwegian)

A long-awaited milestone

Arvid Nesse, CEO in Norwegian Offshore Wind

Norwegian Offshore Wind congratulates both project teams on reaching an important milestone.

“This is an important decision for the next phase of floating wind. Demonstration projects are where technology, operations and industrial capability meet. They allow the industry to identify risks, build experience and test the supply chain before moving into larger wind farms,” says Arvid Nesse, CEO of Norwegian Offshore Wind.

He adds that Enova’s competitions are an important instrument for reducing costs and commercialising floating wind. The decision to support two projects is therefore very welcome, says Nesse:

This is excellent news for the development of floating offshore wind, internationally and nationally. The decision could mark the beginning of a new phase for floating wind in Norway.

Moving up a scale

Enova launched the competition to support projects in the final stage before commercial deployment and to test how different technologies and solutions perform together as an integrated system.

The applications were assessed against two weighted criteria. Cost efficiency, measured as annual energy production per krone of support, accounted for 70 per cent, while innovation and the potential to disseminate knowledge accounted for 30 per cent. Projects were required to include approximately one to five turbines, have a full-lifecycle plan and target start-up within five years. 

According to Arvid Nesse, the projects represent a significant step up from the scale of previous European floating wind demonstrators.

“We are moving from demonstration turbines of up to 10 MW in Europe to the next generation of full-scale projects, with significantly larger turbines and foundations. This is an important step towards making floating offshore wind a more competitive source of power,” he says.

The projects will provide experience with technology, fabrication, assembly, installation, operation and maintenance on a new scale. This can help reduce technical, operational and commercial risk, while contributing to more efficient and standardised solutions for future developments, including Utsira Nord.

METCentre is ready

METCentre has spent several years preparing its test area outside Karmøy for larger demonstration projects.

The site has an investment-ready licence allowing the installation and operation of up to six floating offshore wind turbines, with a total capacity of 82.7 MW, in addition to the existing 2,3 MW Unitech Zephyros turbine. It also has reserved grid capacity and a mature grid-connection project that includes plans for a new 66 kV export cable and associated infrastructure. 

“METCentre has worked systematically over several years to prepare the test site for this type of floating offshore wind project. We have developed and matured the offshore wind site and secured the necessary licences and grid capacity, making it possible to move quickly from project development to construction and power production,” says Cecilia Girard-Vika, Director of METCentre.

METCentre also brings 17 years of experience in full-scale floating wind demonstration. The new projects will elevate the test site into a larger platform for the qualification, industrialisation and commercialisation of the next generation of floating wind technology.

“METCentre’s role is about more than providing space for wind turbines. We actively bring together technology developers, industry, research institutions, authorities and local communities. In this way, we facilitate cooperation, knowledge sharing and technology development across projects,” says Cecilia Girard-Vika.

Our ambition is to develop METCentre into an arena where both offshore wind technology and the surrounding solutions can be tested and improved, from foundations, mooring systems and electrical infrastructure to marine operations, maintenance, environmental monitoring and data collection.

Two projects can build two supply chains

The projects also represent substantial opportunities for the Norwegian supply chain. Physical developments allow companies to qualify products, services and working methods while building experience and references for a growing international market. 

For the Haugalandet region, the projects could generate activity within engineering, fabrication, maritime operations, logistics, installation, electrical systems, operation and maintenance. With a planned combined capacity of around 74 MW, they would also add new renewable power production to the region once operational. 

“These projects represent major opportunities for the Norwegian supply chain. If two different technology concepts are realised in parallel, they can help develop multiple industrial solutions and supply chains, stimulate innovation and strengthen competition,” says Girard-Vika.

This gives Norway another opportunity to take a leading position in the development and industrialisation of floating offshore wind.

Norwegian Offshore Wind and METCentre will facilitate dialogue between the project developers and relevant suppliers. Dedicated supplier activities and meeting places will be announced as the projects mature and their procurement needs become clearer.

“But first, the winners deserve to celebrate,” says Girard-Vika.

Financing

Join our newsletter

Get weekly updates from the industry and other Norwegian Offshore Wind content

Sign up here

Latest news

International

What’s Polish for ‘local content’?

Read more
International

A short Danish tour. A lasting impact.

Read more
International

At the edge of the map, at the centre of the action

Read more